Calculating the Planned Delivery Time - SAP

    https://help.sap.com/saphelp_470/helpdata/en/f3/41b53c4d36265ce10000000a114084/frameset.htm
    calculate the planned delivery time. To calculate the planned delivery time, the system determines the number of days between the order being placed with the vendor and the actual goods receipt for a freely definable combination of vendor, plant, material, purchasing organization and vendor subrange. change the date of the planned delivery time.

Calculating the Planned Delivery Time - SAP Documentation

    https://help.sap.com/erp_hcm_ias2_2014_03/helpdata/en/f8/a7c7536e8e2a4be10000000a174cb4/content.htm
    calculate the planned delivery time. To calculate the planned delivery time, the system determines the number of days between the order being placed with the vendor and the actual goods receipt for a freely definable combination of vendor, plant, material, purchasing organization and vendor subrange.

Planned Delivery Time Calculation - SAP TCodes

    https://www.sap-tcodes.org/tcode/wpdtc.html
    SAP Transaction Code WPDTC (Planned Delivery Time Calculation) - SAP TCodes - The Best Online SAP Transaction Code Analytics

Calculate planned delivery time - SAP TCodes

    https://www.sap-tcodes.org/tcode/fre32.html
    SAP Transaction Code FRE32 (Calculate planned delivery time) - SAP TCodes - The Best Online SAP Transaction Code Analytics

WPDTC Planned Delivery Time Calculation - Tech

    https://it.toolbox.com/question/wpdtc-planned-delivery-time-calculation-010509
    Hello, One of our customers is thinking of using WPDTC (Planned Delivery Time Calculation). I have searched all over the internet and even asked SAP OSS how SAP caculates the new planned delivery times. Some of the calculations I can infer, but others I have no idea how SAP comes up with the number. I have been given no useful information in this...

Automatic calculation of planned delivery time for the ...

    https://it.toolbox.com/question/automatic-calculation-of-planned-delivery-time-for-the-material-master-020508
    My experiences indicated that planned delivery time calculation and update into the material master records shall be carried out through the custom program as the standard feature of SAP is normally not catering for the complex business requirements. Cheers, HT

Planned Delivery Time Evaluation - Archive

    https://archive.sap.com/kmuuid2/3015d3dd-136a-2c10-3cac-ac122fb42ec2/Planned%20Delivery%20Time%20Evaluation.pdf
    SCM – Planned Delivery Time. Planned Delivery Time . In standard SAP, the Planned Delivery Time is the number of days needed to procure the material (Difference between PO Date & GR Date). It’s maintained in various Master data’s: 1. Material Master 2. Vendor Master 3. Purchase Info Record. Primarily the data is taken from . Purchase Info ...

Planned Delivery Time and Working Days - ERP SCM ... - SAP

    https://wiki.scn.sap.com/wiki/display/ERPSCM/Planned+Delivery+Time+and+Working+Days
    Planned delivery time is always based on calendar days and working days (Factory calendar) are never considered. The following times are taken into account for scheduling materials that are procured externally: Processing time required by the purchasing department (workdays) Planned delivery time of the material (calendar days)

SAP PP Scheduling Tutorial - Free SAP PP Training

    https://erproof.com/pp/sap-pp-training/sap-pp-scheduling/
    Dec 07, 2017 · This tutorial is part of free SAP PP course. SAP PP scheduling is used to calculate start date/start time and end date/end time for a production order or operation. Here you will learn about scheduling production operations in SAP ERP. There are two methods of scheduling in SAP and especially in production planning. Basic dates scheduling.

What is the Difference Between PDT (Planned Delivery Time ...

    https://it.toolbox.com/question/what-is-the-difference-between-pdt-planned-delivery-time-trlt-total-replenishment-lead-time-in-sap-fields-are-in-material-master-021216
    Planned delivery time is specified for a single item and is used as part of the MRP calculation when calculating dates on procurement proposals. Total Replenishment Lead time is the length of time that you would expect for a top level assembly to be replenished, this can be the sum of external procurement time and internal Production time.

MRP Plant Parameters : Determining Planned Delivery Time

    https://it.toolbox.com/question/mrp-plant-parameters-determining-planned-delivery-time-041706
    Hi All, In my case, Why MRP calculation will alwasy taken the 'Planned Delivery Time' from Material Master (MRP2 view) rather than the one that maintained in Puchasing Info Record (PIR)? I have checked and made a selection in field 'Determining Planned dlv time' in txn OPPQ (Plant Parameters)-> External Procurement. Can anybody help me to point...

SAP ABAP Program PDTC_REPORT (Planned Delivery Time ...

    https://www.sapdatasheet.org/abap/prog/pdtc_report.html
    SAP ABAP Program PDTC_REPORT (Planned Delivery Time Calculation) - SAP Datasheet - The Best Online SAP Object Repository. The Best Online SAP Object Repository. ABAP; Hierarchy. Software Component Application Component Package. DDIC. Domain Data Element Table Table Cluster/Pool View Search Help.

PDTC - Internal Table for Planned Delivery Time ...

    http://leanx.eu/en/sap/table/pdtc.html
    PDTC - Internal Table for Planned Delivery Time Calculation; Search. SAP Table PDTC Internal Table for Planned Delivery Time Calculation. PDTC (Internal Table for Planned Delivery Time Calculation) is a standard table in SAP R\3 ERP systems. Below you can find the technical details of the fields that make up this table.

Replenishment Lead Time and MRP type - SAP

    https://wiki.scn.sap.com/wiki/display/ERPMan/Replenishment+Lead+Time+and+MRP+type
    The material has procurement type F (External procurement), Purchasing processing time = 0 days, Planned delivery time = 28 days and GR processing time = 3 days. The total replenishment lead time is 31 days and was defined as explained in the blog post Calculation of the Replenishment Lead Time.